Software Project Management Practice Questions for 7th Semester

21+ reviewed Software Project Management questions for the BCA — 7th Semester exam, available in Nepali and English.

Sample questions

Question 1

Risk exposure is calculated as:

जोखिम एक्सपोजर (Risk exposure) कसरी गणना गरिन्छ?

  • Probability x Impact
  • Risk x Cost
  • Time x Cost
  • Risk / Probability

Question 2

Which one is the highest level of Six Sigma?

सिक्स सिग्मा (Six Sigma) को सबैभन्दा उच्च तह कुन हो?

  • Very Good
  • Good
  • Improvement need
  • Virtual Perfection

Question 3

The critical path method is good for:

क्रिटिकल पाथ मेथड (CPM) कस्तो परियोजनाका लागि उपयुक्त हुन्छ?

  • Small project
  • Large project
  • Both small and large projects
  • Medium project only

See the answers and take the full test